Ottawa Teardown Index: The Homes Coming Down, in Numbers

A torn-down home's lot under redevelopment in Ottawa, excavator on site

Ottawa’s building permit files subtract 1,147 homes between January 2023 and September 2026, and add 36,549 in the same period. Teardowns run at about 3 percent of everything the city permits: roughly one home comes down for every 32 that go up. The removals are not spread evenly across the city. Three of every five are in six inner wards, and the ward removing the most homes, Kitchissippi, is also one of the wards adding the most. RentSetGo Property Management builds this page from the City of Ottawa’s open building permit files, retrieved October 25, 2026, and refreshes it quarterly alongside our housing pipeline page.

A torn-down home's lot under redevelopment in Ottawa, excavator on site

This page is the subtraction side of our Ottawa housing pipeline page, which counts the homes being added. One replacement form gets its own page too: the suites going into and beside existing houses, counted on our Ottawa secondary suites page. Here the lens is the other direction: which homes leave, where they leave from, and what kind of buildings they were. For a landlord, a teardown on the street is the earliest visible sign that a neighbourhood’s housing stock, and its competition, is turning over.

How many homes does Ottawa tear down each year?

The count is steady rather than spiking. The permit files record 255 homes removed in 2023, 318 in 2024 and 311 in 2025, and the first nine months of 2026 produced another 263, about 29 a month. Measured against everything Ottawa adds, removals held in a narrow band: 3.11 percent of gross additions in 2023, 2.98 percent in 2024, 3.24 percent in 2025 and 3.25 percent in the first nine months of 2026. Demolition permits tell the same story from the other side. The City issued 1,198 demolition permits across the period, 842 of them for dwellings. The rest cover the garages, sheds and commercial structures that make up most of the remaining demolition work in a city.

Period Homes removed Gross additions Net change Removals as a share of additions Demolition permits Of which dwellings
2023 255 8,191 7,936 3.11% 266 197
2024 318 10,674 10,356 2.98% 352 270
2025 311 9,593 9,282 3.24% 330 221
2026, January to September 263 8,091 7,828 3.25% 250 154
January 2023 to September 2026 1,147 36,549 35,402 3.14% 1,198 842

Bar chart of Ottawa homes removed and demolition permits by year: 255 homes and 266 permits in 2023, 318 and 352 in 2024, 311 and 330 in 2025, and 263 homes and 250 permits in the first nine months of 2026

Homes removed and demolition permits by year, 2023 to September 2026. Homes removed are counted from the dwelling-unit column of the permit files; the method is set out below. Source: City of Ottawa Open Data, Construction, Demolition, and Pool Permits workbooks, retrieved October 25, 2026.

What counts as a teardown in this index?

A home counts as removed when a permit record subtracts dwelling units in the City’s D.U. column, the net dwelling units field the permit files carry for every record. That is the primary measure on this page, and it is the same column, counted the same way, as the net figures on the housing pipeline page: gross additions minus homes removed equals the net new dwellings figure for every period in the table above. The cross-check is the demolition permit itself, a permit whose description says demolish or demolition. The two signals overlap heavily, but they are not the same count, and the difference is informative.

Of the 1,147 homes removed, 1,063 (93 percent) were subtracted on dwelling-demolition permits. Another 35 sat on other demolition permits, mixed or non-residential buildings that carried homes. The remaining 49 were subtracted on records with no demolition in them at all: permit revisions that withdrew a previously permitted unit, suites merged into one larger home, and houses converted to office or retail space. That last slice is small in every year but visibly larger in 2026, with 29 of the 49, because apartment and suite revisions have grown. In the other direction, most demolition permits remove no home at all: garages and sheds dominate the non-dwelling permits, and a dwelling demolition occasionally records its units on a companion record instead.

One distinction matters before anyone quotes these numbers. This page counts Building Code demolition permits. “Demolition Control” in the City’s development applications system is a separate planning approval for tearing down residential buildings, a different instrument in a different dataset, and it is not counted here. The applications side of the planning system, including demolition control files, is tracked on our Ottawa development applications page.

Where are Ottawa’s homes coming down?

Kitchissippi, in the city’s west end, removes more homes than any other ward: 218 between January 2023 and September 2026, on 210 demolition permits. Rideau-Vanier follows at 170 and Rideau-Rockcliffe at 104. Six inner wards (Kitchissippi, Rideau-Vanier, Rideau-Rockcliffe, Capital, River and Bay) account for 701 of the 1,147 homes removed, 61 percent of the city total. These are the established wards where the housing stock is old, lot values are high, and a house that comes down is usually worth more as a site than as a building. Kitchissippi covers neighbourhoods such as Westboro and Hintonburg, the streets covered by our Westboro property management page.

Ward Homes removed Gross additions Net change Demolition permits
Ward 15, Kitchissippi 218 2,161 1,943 210
Ward 12, Rideau-Vanier 170 2,619 2,449 108
Ward 13, Rideau-Rockcliffe 104 1,215 1,111 71
Ward 17, Capital 73 895 822 82
Ward 16, River 70 1,542 1,472 73
Ward 7, Bay 66 937 871 76
Ward 5, West Carleton-March 59 347 288 74
Ward 14, Somerset 44 3,252 3,208 50
Ward 21, Rideau-Jock 44 1,496 1,452 59
Ward 8, College 41 1,007 966 53

Horizontal bar chart of the top 10 Ottawa wards by homes removed, January 2023 to September 2026, led by Kitchissippi at 218 and Rideau-Vanier at 170

Top 10 wards by homes removed, January 2023 to September 2026, with demolition permit counts. Source: City of Ottawa Open Data, Construction, Demolition, and Pool Permits workbooks, retrieved October 25, 2026.

Two rows in the table break the inner-ward pattern, in opposite directions. Somerset added more homes than any other ward in the city, 3,252, while removing only 44: downtown supply is landing mostly on land that was not houses. West Carleton-March, a rural ward, removed 59 homes against just 347 additions, a pattern of individual lot rebuilds rather than redevelopment. The teardown-to-multi-unit pattern belongs to the inner wards in between.

The 2026 picture so far

Nine months into 2026, the order at the top has flipped. Rideau-Vanier leads the city with 84 homes removed, ahead of Kitchissippi at 39, and the reason is building size rather than permit count. Two apartment demolitions in Rideau-Vanier removed 30 and 15 homes between them, 45 of the ward’s 84. Rideau-Vanier is also the ward with the second-deepest renter pool in the city, as our Ottawa renters by ward page shows, so its demolitions subtract from rental-heavy stock. Across the full period, the largest single removal in the files took down a 32-unit apartment building in Rideau-Rockcliffe. Only 15 records in 45 months removed five or more homes, but they account for 158 homes, 14 percent of all removals.

What gets torn down?

Mostly one house at a time. Of the 863 records that subtract homes, 752 (87 percent) remove exactly one. By the building type recorded on the permit, single homes account for 440 of the removed homes on 425 records, and permits the City files under a building type literally called “Demolition” account for another 441 on 355 records. Apartment buildings are the mirror image of the single-house pattern: just 33 records, but 159 homes, because one permit takes down a whole building. Duplexes account for 40 homes, semi-detached homes for 31, rowhouses for 14, and the remaining types are in single digits.

Building type, as recorded on the permit Homes removed Removal records
Demolition (the City’s own type label for many demolition permits) 441 355
Single 440 425
Apartment buildings 159 33
Duplex 40 20
Semi-detached 31 17
Rowhouse (including stacked) 23 8
All other types 13 5

What replaces the homes that come down?

Citywide, the arithmetic is lopsided: about 32 homes added for every one removed. The ward table shows where that replacement is concentrated. The six inner wards that lead removals also took 9,369 additions over the same period, 26 percent of everything Ottawa permitted, so on the streets where homes come down, new homes are also going up at the fastest rate. The form of the replacement is visible on the sister pages of this one: Kitchissippi, the teardown leader, also added the most secondary-suite units of any ward in 2025, as teardown sites are rebuilt and houses go up with suites designed in. Read at ward level, the pattern is houses down and more units up. Two cautions keep that statement honest. This page does not track individual lots, so it cannot say what replaced any specific demolished home; some replacements are a single larger house, and some teardown sites sit empty for a time. And in the rural wards the pattern does not hold at all: removals there are mostly one-for-one rebuilds.

What this data can’t tell you

Three limits matter. First, a permit authorizes a demolition; it does not confirm the building came down. The files record permit issuance, not completion, and a permitted demolition can stall or be abandoned. Second, the count is a floor with a small gap, not an exact registry. The dwelling-unit column is net per permit record, so a home removed inside a combined demolish-and-build permit would show only in that permit’s net figure. Ottawa almost always permits demolition as its own permit first (one combined dwelling case appears in 45 months of files), which keeps the gap small, and a demolition done with no permit at all never appears in the files. Third, nothing in a permit says whether the home was rented, owned or vacant, or when the work happened. The rental effect of 1,147 removed homes is real but indirect: it lands through the new product that follows on those streets, which the pipeline and secondary-suites pages count.

What This Means if You Own a Rental in Ottawa

The figures above are measurements. What follows is our reading of them for Ottawa landlords, labelled as interpretation throughout.

Teardowns are a drip, not a wave

Removals held between 2.98 and 3.25 percent of gross additions in every period counted. Nothing in the files suggests demolition is shrinking Ottawa’s housing stock: the city added about 32 homes for every one it removed, for a net gain of 35,402 dwellings. A landlord does not need a demolition strategy. A landlord in the wrong ward does need to watch the street-level pattern below.

The pressure is concentrated in six inner wards

Kitchissippi, Rideau-Vanier, Rideau-Rockcliffe, Capital, River and Bay hold 61 percent of all removals. If your rental is in one of them, a teardown nearby is a normal event, and the replacement is usually more units than came down: those same wards took 9,369 additions in the period. Price and renovate assuming the competing stock on your street is getting newer and denser. Outside those wards, teardowns are a rarity and mostly one-for-one rebuilds.

Suites are part of the replacement product

The ward that removes the most homes also leads the city in new secondary-suite units. Builders working teardown sites in the inner wards are building houses that hold two or three households where one stood. For an owner of an older single or duplex nearby, that is the competitive fact: the new house across the street may be two or three listings, not one.

Watch the handful of large apartment demolitions

Fifteen records in 45 months removed 158 homes. When an older low-rise apartment building is demolished in a renter-heavy ward, as happened twice in Rideau-Vanier in 2026, rental stock leaves in a single step and the households in it look for new homes in the same market you lease into. It is infrequent enough to track by name of ward, and material enough to matter when it lands near a property you own.

When this is a watch item, not an action item

If your property is tenanted on a stable lease in a ward with few teardowns, nothing here asks you to act. The count matters at decision points: buying on a street where houses are coming down and multi-unit product is going up, renovating a unit that will compete with that product, or a vacancy in a ward where a large demolition just tightened the local stock. That is where our property management service earns its fee, pricing and leasing against the local turnover picture instead of the citywide average.

The Bottom Line

Ottawa tears down about 300 homes a year and permits about 10,000, and both sides of that ledger concentrate in the same inner wards. Kitchissippi removes the most homes and adds among the most; Rideau-Vanier leads in 2026 on the strength of a few large apartment demolitions; Somerset builds heavily while barely demolishing at all. The teardown itself is rarely the story for a landlord. The story is what follows it onto the street: newer, denser product, increasingly with suites built in, competing for the same tenants. This page is refreshed quarterly alongside the Ottawa housing pipeline page; the figures above are the October 25, 2026 retrieval, covering January 2023 to September 2026.

Frequently Asked Questions

How many homes were demolished in Ottawa in 2025?

Ottawa’s permit files record 311 dwelling units removed in 2025, and the City issued 330 demolition permits that year, 221 of them for dwellings. The two numbers measure different things: the first counts homes subtracted on permit records, the second counts permits, most of which remove one home but many of which remove none (garages, sheds and other structures). The files were retrieved October 25, 2026.

Which Ottawa ward has the most teardowns?

Kitchissippi (Ward 15), with 218 homes removed between January 2023 and September 2026, followed by Rideau-Vanier (Ward 12) at 170 and Rideau-Rockcliffe (Ward 13) at 104. In the first nine months of 2026, Rideau-Vanier leads with 84 homes removed, 45 of them in two apartment demolitions.

What is the difference between a demolition permit and Demolition Control?

A demolition permit is a Building Code permit authorizing the physical demolition of a structure; this page counts those permits and the dwelling units recorded on them. Demolition Control is a separate planning approval in the City’s development applications system, required before residential demolition in parts of the city. It is a different instrument in a different dataset and is not counted here.

Does a demolition permit mean the home is already gone?

No. A permit authorizes the work; the permit files record the issue date, not a completion inspection, and some permitted demolitions stall or are never carried out. The counts on this page are permits issued and units recorded in each period.

Are all removed homes demolished houses?

No. 1,063 of the 1,147 homes removed (93 percent) were subtracted on dwelling-demolition permits. The rest were subtracted on other records: permit revisions, units merged into larger homes, and houses converted to office or retail space. And most teardowns are small: 752 of the 863 removal records (87 percent) remove exactly one home.

How often is this page updated?

Quarterly, alongside the Ottawa housing pipeline page, as the City publishes new permit files. This edition covers January 2023 to September 2026 and uses files retrieved October 25, 2026.

Own a Rental on a Street Where the Houses Are Coming Down?

RentSetGo Property Management manages rentals across Ottawa, including the inner wards where teardown and rebuild activity is concentrated. We price each property against its own street picture: the homes coming down nearby, the units replacing them, and the suites being built into the new houses, then handle the listing, screening, leasing and day-to-day management from there.

Send us the address of a property you own or are assessing. We will return a free rental appraisal covering the property as it stands and, where teardown sites nearby are being rebuilt as multi-unit product, what that incoming competition does to the rent picture.

613-800-2523 · info@rentsetgo.ca

BOOK A CALL GET A FREE RENTAL APPRAISAL

Managing rentals for local, out-of-province and non-resident owners across Ottawa, including teardown-heavy wards such as Kitchissippi, Rideau-Vanier and Rideau-Rockcliffe.

Related Reading

Data: City of Ottawa Open Data, Construction, Demolition, and Pool Permits workbooks (2023 file; 2024 to 2025 file; 2026 file), retrieved October 25, 2026; contains information licensed under the Open Government Licence – Ottawa. A home is counted as removed when a permit record subtracts dwelling units in the files’ D.U. column; demolition permits are counted separately, by permit description, and the two measures are reported side by side rather than merged. A building permit authorizes demolition; it does not confirm that a building was demolished, and the source files carry no completion, occupancy or tenure information. 2026 figures cover January to September. Figures change as the City revises its files. This page is general information about Ottawa housing supply, not legal, tax, insurance or investment advice. Consult a licensed paralegal or lawyer, an accountant, or an insurance broker for advice on your own property.

Looking for a Property Manager?

Unlock a property management strategy that is as refined and reliable. If you are an owner looking for a trusted local partner we are here to guide you. Simply fill out the form to begin your journey with us. Your premier property solution in the heart of the Ottawa is just a few clicks away!